Field measurements and modeling studies of 12th phase of southern pars

Hydrodynamic and sediment studies, environmental impact assessment and structure design of kish taban hotel marina
September 16, 2018
Environmental Impact Assessment (EIA) for Abouzar – Ilam Pipeline Renewal Project
December 17, 2022
 

Monitoring & Modeling Studies of Khuzestan Province Coastlines

1PROJECT TITLE
Field measurements and modeling studies of 12th phase of southern pars
2LOCATION
PARS SPECIAL ENERGY ZONE, BUSHEHR, IRAN
3CLIENT
PETROPARS COMPANY
4THE DATE OF EXECUTION
OCTOBER 2007 - FOR 3 MONTH
5THE PERFORMED SERVICES BY DNP
WAVE AND CURRENT MEASUREMENT IN STATIONS
MEASUREMENT OF METEOROLOGICAL PARAMETERS IN ONE STATION
SEDIMENT SAMPLING IN 56 POINTS
SEDIMENT SAMPLING BY USING SEDIMENT TRAP IN POINTS
FLOAT TRACKING OPERATION IN POINTS
CTD PROFILING IN STATIONS TWICE A DAY
HYDROGRAPHIC SURVEY WITHIN STUDIED AREA
MODELING WITHIN STUDIED AREA
 
 
 
 